Earned Value and Tolerance, using critical path

Filed under: Project Management — Tags: — admin @ 09:09

When reporting on earned value, more often than not, the project is slightly behind the original plan and the earned value is below the planned value.
How does the project manager and the project stakeholders know if the variance is within the tolerance of the project or not? What is the bottom-line?…

The project critical path can be used, in order to represent the tolerance threshold, as in the example below.

Values for the chart can be automated using MS Project and MS Excel… See previous post on earned value calculationĀ http://www.casoft.com.au/2009/04/calculate-earned-value-with-tfs.html

For more information contact us – jjacquet AT casoft.com.au

Share and Enjoy:
  • Print
  • Digg
  • StumbleUpon
  • Add to favorites
  • Facebook
  • Yahoo! Buzz
  • Twitter
  • Google Bookmarks
  • LinkedIn
  • email

No Comments »

No comments yet.

RSS feed for comments on this post. TrackBack URL

Leave a comment

Powered by WordPress and Writeup.com.au